From Indiatimes · Surendra Singh · · 2m
Kaiga Unit-1 Returns to Criticality
Kaiga nuclear unit-1 achieves criticality after 25 years, setting new operational benchmark.
In brief
Kaiga nuclear unit-1 achieves criticality after 25 years, setting new operational benchmark. Kaiga Generating Station Unit-1 reached criticality for the second time after 25 years of operation, completing major refurbishment in 600 days. Originally reported by Indiatimes.
Kaiga Unit-1 Attains Criticality
Kaiga Generating Station Unit-1 (KGS-1) in Karnataka successfully attained criticality for the second time after 25 years of operation.
Unit-1 Operational History
KGS-1 reached first criticality on September 26, 2000, and supplied 37,670 million units before shutdown in April 2025.
World Record Operation
The unit previously set a world record for 962 days of continuous operation at 99.3% plant load factor in December 2018.
Refurbishment Completion
KGS-1 completed major refurbishment activities including EMCCR and EMFR replacements on April 1, 2025, after 600 days of shutdown.
NPCIL Statement
NPCIL stated KGS-1 set a new fleet-wide benchmark as the first reactor to reach criticality within 600 days of major refurbishment.
Technical Achievement
The unit achieved criticality after completing en-masse coolant channel replacement and feeder replacement systems.
KGS-1 Capacity
Kaiga Generating Station has four operational units totaling 880 MW with two additional units under construction.
Indigenous Reactors
Units-5 and 6 are state-of-the-art indigenous 700 MW pressurized heavy-water reactors with advanced safety features.
The main idea
Kaiga Generating Station Unit-1 reached criticality for the second time after 25 years of operation, completing major refurbishment in 600 days.