Chow Kon Yeow defends Penang’s RM8.4b water deal
Penang CM says water payments cover plant costs over 40 years.
In brief
Penang CM says water payments cover plant costs over 40 years. Penang Chief Minister Chow Kon Yeow states the RM8.4 billion water deal payments cover plant construction costs over 40 years, with annual RM210 million fees separate from water supply charges. Originally reported by Malay Mail.
Penang water deal
Penang Chief Minister Chow Kon Yeow defends the RM8.4 billion water deal with Perak, stating payments cover plant costs over 40 years.
Annual payment
The RM210 million annual payment is an 'availability payment' for the plant’s capacity, separate from water supply charges.
Plant construction

The water treatment plant, with 500 million litres per day capacity, cost RM3 billion to build exclusively for Penang.
Payment mechanism
The RM8.4 billion figure includes financing costs and plant renewal over 40 years, with financial consultants reviewing the project.
Safeguards
The agreement includes compensation for water shortfalls and termination rights if Perak breaches the contract.
Supply charge
The RM16.2 billion supply charge covers water received meeting quality standards, separate from the capacity payment.
Termination clause
PBAPP can terminate the agreement if Perak breaches contract and fails to fix within 90 days.
Renegotiation
If water supply suspends for over three months, either party may request renegotiation of the agreement.
Payment alternative
If renegotiation fails, PBAPP pays one-off discounted balance instead of annual payments until 2072.