Mizoram to get piped gas by 2028

Mizoram will receive piped cooking gas connections by early 2028 under a ₹491 crore pipeline project.

6 cards · 1m · tap to begin

From · · · 1m

Mizoram to get piped gas by 2028

Mizoram will receive piped cooking gas connections by early 2028 under a ₹491 crore pipeline project.

In brief

Mizoram will receive piped cooking gas connections by early 2028 under a ₹491 crore pipeline project. Mizoram will get piped natural gas for cooking by early 2028 through a ₹491 crore pipeline connecting Mamit and Aizawl districts. Originally reported by The Economic Times.

Mizoram gas pipeline progress

Mizoram will get piped natural gas connections for cooking by early 2028 under the Northeast Gas Grid Project.

Pipeline construction underway

Indradhanush Gas Grid Limited is building a 119.45-km pipeline linking Panisagar in northern Tripura with Aizawl.

Mizoram gas shortage issue

Global conflicts have caused periodic LPG shortages in Mizoram, affecting domestic cooking arrangements.

Pipeline cost and coverage

The project will cost ₹9,265 crore to lay 1,656 km of pipelines across Northeastern states, with ₹491 crore for Mizoram.

Timeline for pipeline completion

The pipeline will reach Mamit town by March-April 2027 and Sihhmui in Aizawl district by March-April 2028.

Gas access benefits

Piped gas will provide cleaner cooking fuel and enable compressed natural gas for vehicles in Mizoram.

The main idea

Mizoram will get piped natural gas for cooking by early 2028 through a ₹491 crore pipeline connecting Mamit and Aizawl districts.

Read the original on The Economic Times

React

Sign in to react and comment.

Comments (0)

Life is short. Keep it sweet. Respect others' opinions and be kind!

    Recommended next

    More decks on mizoram and related topics.