Ujjain airport upgrade stalls over environmental gaps
A ministry panel has deferred approval for the Ujjain airport expansion ahead of the 2028 Kumbh, citing inadequate wildlife studies and unaddressed local concerns.
In brief
A ministry panel has deferred approval for the Ujjain airport expansion ahead of the 2028 Kumbh, citing inadequate wildlife studies and unaddressed local concerns. India's Environment Ministry panel has deferred clearance for the Ujjain airport upgrade, demanding detailed wildlife surveys and responses to local…
Ministry panel defers airport approval
An expert appraisal committee of the Union Environment Ministry has deferred its decision on clearing the Ujjain airport upgrade, citing inadequate responses to public concerns and incomplete environmental studies.
The project and its scope
The Airports of India proposes to extend the runway from one thousand seventy-seven metres by twenty-three metres to one thousand eight hundred metres by forty-five metres, build a new terminal and support facilities at an…
Kumbh deadline drives the timeline

The upgrade is planned ahead of the two thousand twenty-eight Simhasta Kumbh in Ujjain, the hometown of Madhya Pradesh Chief Minister Mohan Yadav, to handle crores of religious tourists.
Distance rule compliance questioned
The committee noted that the proposal did not demonstrate compliance with Civil Aviation guidelines requiring no greenfield airport within an aerial distance of one hundred fifty kilometres of an existing civilian airport.
Wildlife data contradicts project claims
The Airports of India stated no Schedule-I species were present in the ten-kilometre buffer, but the divisional forest officer, Ujjain, reported the presence of Blackbuck, a Schedule-I species in the area.
Committee demands detailed fauna survey
The expert appraisal committee directed the Airports of India to undertake a detailed fauna survey and submit a site-specific wildlife conservation plan in consultation with the local forest department.
Local concerns remain unaddressed
During a public hearing on September eighteen, locals and project-affected persons raised issues about adequate compensation, construction of an approach road and access to agricultural land, which the committee found were not properly addressed.
“issues raised by locals and project-affected persons during the public hearing held at the project site on September 18 were not "addressed/replied properly."”
Committee demands stakeholder response plan
The expert appraisal committee directed the Airports of India to submit a detailed report addressing stakeholder issues, specific commitments to resolve them, adequate budgetary provisions and a time-bound action plan for implementation.
Environmental management plan must be revised
The committee also directed the Airports of India to revise the Environmental Management Plan to incorporate all suggestions and mitigation measures, and submit a detailed tree survey report with a compensatory tree plantation proposal.
Projected passenger capacity and operations
The upgraded airport is estimated to operate twenty scheduled commercial flights per day during the initial phase, handling approximately seven thousand three hundred aircraft movements per year and five hundred forty-three thousand five hundred annual…
Next step: Airports of India must respond
The Airports of India must now provide the detailed environmental and wildlife studies, address local concerns and revise its management plans before the expert appraisal committee will reconsider the proposal for final clearance.
The short version
India's Environment Ministry panel has deferred clearance for the Ujjain airport upgrade, demanding detailed wildlife surveys and responses to local objections before proceeding.