# Army gets 180 tank rounds instead of 12,000

> The Pentagon's new ammunition for Abrams tanks is years late. A watchdog found just 180 of nearly 12,000 rounds delivered by July.
- Title: Army gets 180 tank rounds instead of 12,000 · Business Insider
- Summary: The Pentagon's new ammunition for Abrams tanks is years late. A watchdog found just 180 of nearly 12,000 rounds delivered by July.
- Keywords: us army, abrams tank, 120mm advanced multi-purpose round, northrop grumman, pentagon watchdog, ammunition delays, defense contracting, Business Insider
- URL: https://shortify.news/Business_Insider/army-gets-180-tank-rounds-instead-of-12000
- Source: Business Insider — https://businessinsider.com/army-abrams-tank-ammunition-delays-northrop-2026-11
- Author: Kelsey Baker
- Published: 2026-11-27T20:43:44.55+00:00
- Read time: 1 min
- Topics: us army, abrams tank, 120mm advanced multi-purpose round, northrop grumman, pentagon watchdog, ammunition delays, defense contracting, business, technology
## Army expected 12,000 rounds by summer
The US Army was scheduled to receive nearly 12,000 new 120mm Advanced Multi-Purpose rounds by July. The ammunition was designed to replace several older types and give Abrams tank crews more flexibility in combat.
## Contractor delivered just 180 rounds
As of late July, Northrop Grumman had delivered only 180 of the nearly 12,000 rounds scheduled for delivery by that time, according to a Pentagon watchdog report released recently.
## Deliveries delayed over three years
The Army only accepted its first rounds in December 2024, over three years after deliveries were originally due. Production problems and leaking primer material found during testing in 2025 contributed to the delays.
## Army awarded more rounds despite poor performance
Despite the delays, the Army awarded Northrop another contract in March for 10,000 more rounds. Army assessment reports rated the contractor's performance as marginal or unsatisfactory in five of seven reviews since 2018.
## Pentagon may not get full value from contract
Because of delays and technical challenges, the Pentagon may not receive the full value from the nearly 224 million dollars that has been obligated for the contract for over a decade.
## Key takeaway

The Army received only 180 of nearly 12,000 new tank rounds scheduled for delivery by July, years behind schedule due to contractor production problems.

---

Summary: Shortify — https://shortify.news/Business_Insider/army-gets-180-tank-rounds-instead-of-12000
Reporting: Business Insider — https://businessinsider.com/army-abrams-tank-ammunition-delays-northrop-2026-11

When you use this summary, link the Shortify URL for the summary and credit the reporting to its newsroom.