# Google ordered to stop Belgium datacentre build

> Belgian authorities halt construction on a major Google datacentre after the tech firm continued work without proper planning approval.
- Title: Google ordered to stop Belgium datacentre build · the Guardian
- Summary: Belgian authorities halt construction on a major Google datacentre after the tech firm continued work without proper planning approval.
- Keywords: google, belgium, datacentre, wallonia, planning permit, greenpeace, water cooling, aiseau-presles, the Guardian
- URL: https://shortify.news/the_Guardian/google-ordered-to-stop-belgium-datacentre-build
- Source: the Guardian — https://theguardian.com/world/2026/nov/27/belgian-authorities-order-google-to-halt-datacentre-construction-over-lack-of-permits
- Published: 2026-11-27T17:21:18+00:00
- Read time: 1 min
- Topics: google, belgium, datacentre, wallonia, planning permit, greenpeace, water cooling, aiseau-presles, news, world
## Google halts Belgium datacentre work
Belgian authorities ordered Google to stop construction on a large datacentre in Wallonia after the company continued building without approved planning permission modifications.
## Building nearly complete despite permit refusal
Inspectors found the three hectare structure almost finished with structural work completed, even though the permit had been refused. Three hundred workers received verbal and written stop orders.

> Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused
## Google switched cooling method in twenty twenty-five
Google's twenty twenty-five application proposed merging two smaller air-cooled datacentres into one larger facility using water cooling, drawing six hundred cubic metres hourly from the Sambre River.
## Permit revoked over drought concerns
Regional authorities initially approved the amendments in April, but residents and protest groups appealed. In August, Wallonia infrastructure minister François Desquesnes revoked the modified permit over drought concerns.
## Greenpeace exposed ongoing construction
Greenpeace published a report with drone footage showing Google continued construction despite lacking correct permits. The environmental group filed an emergency appeal with local planning authorities.

> The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked
## Court ruling expected January seventh
Google appealed the permit revocation to Belgium's council of state. A ruling in the case is expected on seven January, with prosecutors investigating allegations of illegal construction covering three hectares.
## Key takeaway

Belgian authorities ordered Google to halt datacentre construction in Wallonia after the company continued building without approved permits, with a court ruling expected January seventh.

---

Summary: Shortify — https://shortify.news/the_Guardian/google-ordered-to-stop-belgium-datacentre-build
Reporting: the Guardian — https://theguardian.com/world/2026/nov/27/belgian-authorities-order-google-to-halt-datacentre-construction-over-lack-of-permits

When you use this summary, link the Shortify URL for the summary and credit the reporting to its newsroom.