# India's bullet train trial runs set for April 2027

> The indigenously made high-speed train for the Mumbai-Ahmedabad corridor will begin test runs on the Surat-Bilimora section next year.
- Title: India's bullet train trial runs set for April 2027 · The Hindu
- Summary: The indigenously made high-speed train for the Mumbai-Ahmedabad corridor will begin test runs on the Surat-Bilimora section next year.
- Keywords: bullet train, mumbai-ahmedabad corridor, surat-bilimora, high-speed rail, beml, ashwini vaishnaw, trial runs, india railways, The Hindu
- URL: https://shortify.news/The_Hindu/indias-bullet-train-trial-runs-set-for-april-2027
- Source: The Hindu — https://thehindu.com/news/national/trial-runs-for-high-speed-surat-bilimora-train-to-begin-in-april-may-2027-railway-minister/article71735387.ece
- Author: Maitri  Porecha
- Published: 2026-11-23T15:49:23+00:00
- Read time: 2 min
- Topics: bullet train, mumbai-ahmedabad corridor, surat-bilimora, high-speed rail, beml, ashwini vaishnaw, trial runs, india railways, news, politics
## Trial runs begin next year
India's first domestically made high-speed train will begin trial runs in April and May twenty twenty-seven on the Surat-Bilimora section, Railway Minister Ashwini Vaishnaw announced on Monday, November thirteen, twenty twenty-six.
## Fifty kilometres in six minutes
The high-speed train will cover the fifty kilometre stretch between Surat and Bilimora in about six minutes, compared to forty-five minutes to one point five hours for regular trains currently on the route.
## Public service by Independence Day
Sources indicated the high-speed rail service may open to the public as early as Independence Day, August fifteen, twenty twenty-seven, though this has not been officially confirmed.
## Made in India at BEML facility
Manufacturing of rolling stock for the B twenty-eight train is underway at the Aditya manufacturing facility run by BEML in Bengaluru. Signalling systems work will finish by January end twenty twenty-seven.
## Surat to Bilimora, not Vapi
The trial section was scaled back from the originally planned Surat to Vapi stretch of almost one hundred twenty kilometres due to non-completion of work and delays, a senior official told The Hindu.
## Full corridor spans five hundred eight kilometres
The entire bullet train corridor between Mumbai and Ahmedabad spans five hundred eight kilometres and will take approximately two hours to traverse when fully operationalised. The National High Speed Rail Corporation Limited is constructing it.
## Train passed critical squeeze test
BEML-made train sets recently passed a squeeze test, which subjects the train car body to double the pressure that could occur at speeds beyond two hundred forty kilometres per hour to test structural strength and…

> Such trains need to have a capability to sustain this heavy pressure.
## Japan's E5 series plan delayed
India was originally set to receive Japanese Shinkansen E five series train sets that run at speeds up to three hundred twenty kilometres per hour.
## Indigenous manufacturing chosen over imports
India decided to manufacture indigenous high-speed train sets after negotiations with Japanese counterparts stagnated on multiple grounds, including the costs of acquiring the train sets.
## Key takeaway

India's first domestically manufactured bullet train will begin trial runs in April and May twenty twenty-seven on the fifty kilometre Surat-Bilimora section.

---

Summary: Shortify — https://shortify.news/The_Hindu/indias-bullet-train-trial-runs-set-for-april-2027
Reporting: The Hindu — https://thehindu.com/news/national/trial-runs-for-high-speed-surat-bilimora-train-to-begin-in-april-may-2027-railway-minister/article71735387.ece

When you use this summary, link the Shortify URL for the summary and credit the reporting to its newsroom.