# She was building her dream home. Then came a data center's 'minor' power plant

> Texas neighbor fights data center's hidden power plant permit loophole.
- Title: She was building her dream home. Then came a data center's…
- Summary: Texas neighbor fights data center's hidden power plant permit loophole. Merrie Saltana's family faces displacement after a data center's minor power plant…
- Keywords: data centers, texas, power plants, minor source permits, air pollution, bastrop county, pacifico energy, anthropic, news, politics, world, building
- Source: Straight Arrow — https://san.com/cc/she-was-building-her-dream-home-then-came-the-data-center-inside-a-key-loophole-for-minor-power-plants
- Published: 2026-10-18T13:00:00+00:00
- Read time: 2 min
- Topics: data centers, texas, power plants, minor source permits, air pollution, bastrop county, pacifico energy, anthropic, news, politics, world
## Merrie Saltana's dream home
Merrie Saltana was three days from pouring concrete for her family's dream home when she heard about a data center's proposed power plant across the street.

> Welcome to my little piece of Heaven, for now.
## Data center power plant
The Pacifico Energy power plant, set to run 30% to 80% of the year, will produce 1.3 gigawatts of electricity for Anthropic's data center.

> It was like somebody punched me in the gut.
## Minor source permit
Texas regulators approved the power plant under a minor source permit, which requires no public notice or comment period before construction.

> None of these projects are being considered holistically.
## Regulatory loophole
Data centers use minor source permits to avoid public input, allowing them to build power plants without community oversight.

> It’s allowed for a lot of loopholes and problematic determinations about what’s major and minor.
## Cumulative pollution
Environmental groups warn that splitting large power installations into multiple minor permits leads to unreviewed cumulative pollution impacts.

> There’s a big risk for air pollution to be worse than it would be if these were more regulated.
## Texas regulatory surge
Texas saw a surge in minor source permits for data center power plants from 30 to 90 applications per year (2016-2023) to 158 in 2025.

> In 2024 the agency received 122, followed by 158 in 2025.
## Neighbors' concerns
Residents in Bastrop County worry about air pollution and the lack of community input for the Pacifico power plant.

> I feel very dependent on these guys that are so knowledgeable and are really doing all the hard work.
## Legal challenges
Environmental groups are challenging data centers for splitting power plants into multiple minor permits to avoid cumulative emissions reviews.

> All of these generators are going to be on the same property and serving no other purpose other than powering Amazon’s facility.
## Regulatory process
Texas regulators require no public notice or comment period for minor source permits, leaving residents with limited ability to challenge the project.

> The only changes in the neighborhood were the surveying flags on the project site fluttering in a mellow breeze.
## Power plant capacity
Pacifico's 48 turbines will generate 1.3 gigawatts of electricity, comparable to the largest nuclear reactors in the U.S.

> Pacifico’s turbines will be on par with the largest nuclear reactor units in the U.S.
## Public meeting
Residents held a meeting on October 7, 2026, to discuss the Pacifico power plant and data center project.

> Part of our methodology has been to throw sand in gears and just slow this thing down.
## Health impacts
A report estimates 177 gigawatts of gas power plants could lead to $5.6 billion in annual healthcare costs due to air pollution.

> It might be conservative because this lack of oversight we’re talking about could lead to them emitting more than is in their permitted limit.
## Construction timeline
The Pacifico power plant is pending approval as of mid-October 2026, with construction expected to begin in November.

> The power plant and data center campus are looking to move forward with the first phase of construction at the end of November.
## Community impact
Residents face displacement risks as the data center and power plant threaten their homes and community.

> Who’s gonna want to buy next to a data center, especially this type of data center next to a power plant?
## What happens next
Texas regulators are pausing data center approvals while they audit grid connections, with the Pacifico project pending approval until December.

> The audit is expected to wrap up in December.
## Key takeaway

Merrie Saltana's family faces displacement after a data center's minor power plant, approved without public input, threatens their home in Bastrop County, Texas.