# South Africa's renewable developers locked out of Eskom's biggest deal

> Eskom's 6GW Green RFQ favours global giants over local developers who built the country's independent power industry.
- Title: South Africa's renewable developers locked out of Eskom's…
- Summary: Eskom's 6GW Green RFQ favours global giants over local developers who built the country's independent power industry.
- Keywords: eskom, eskom green, renewable energy, south african developers, solar pv, wind energy, battery storage, independent power producers, procurement, energy policy, Daily Maverick
- URL: https://shortify.news/Daily_Maverick/south-africas-renewable-developers-locked-out-of-eskoms-bigg
- Source: Daily Maverick — https://dailymaverick.co.za/article/2026-11-23-eskom-green-rfq-local-renewable-energy-developers-locked-out-by-eskom-rules
- Author: Chris Yelland
- Published: 2026-11-23T22:33:52+00:00
- Read time: 3 min
- Topics: eskom, eskom green, renewable energy, south african developers, solar pv, wind energy, battery storage, independent power producers, procurement, energy policy, news, politics
## Eskom's six gigawatt opportunity
On two October twenty twenty-six, Eskom issued a request for qualification to select strategic partners for Eskom Green, its new renewable energy subsidiary.
## The 240 megawatt killer
Eskom's qualifying rules impose a 240 megawatt minimum through pass-or-fail criteria. Only one operational solar or wind project of that size exists in South Africa: the 240 megawatt Mooi Plaats solar plant near Noupoort, which…

> only one operational solar PV or wind project of that size exists in South Africa
## Why local developers fail
South Africa's renewable fleet is a portfolio of mid-sized plants because REIPPPP capped individual projects at 75 megawatts for solar and 140 megawatts for wind.Local developers built rationally to government specifications.
## SOLA Group falls short
SOLA Group has about 600 megawatts operational, but its largest plant, Springbok, is 195 megawatts. Its 300 megawatt hybrid project Naos-1 is due in twenty twenty-eight, after the closing date of twelve January twenty twenty-seven.
## Red Rocket's timing problem
Red Rocket has 530 megawatts operational, led by the 144 megawatt Brandvalley and Rietkloof wind farms. Its 242 megawatt Overberg wind farm is due in early twenty twenty-seven, after the closing date.
## NOA Group's buyer problem
NOA Group's 157 megawatt Khauta West and 349 megawatt Khauta South solar plants reach commercial operation in late twenty twenty-six and early twenty twenty-seven.
## Seriti Green and Mulilo Energy
Seriti Green's 155 megawatt first phase of Ummbila Emoyeni wind farm entered operation only in twenty twenty-six.Mulilo Energy has about 448 megawatts operational, mostly REIPPPP-sized plants.
## Pele Green Energy's partial path
Pele Green Energy holds 20 percent of the 240 megawatt Mooi Plaats solar plant.Eskom counts a project's full capacity regardless of equity share, so Mooi Plaats could count if Pele can prove a co-developer role.
## International players will lead
Eskom's eligibility criteria work in favour of companies with large global portfolios.Experience anywhere in the world counts, and no South African experience is needed.
## Copenhagen Infrastructure Partners' advantage
Copenhagen Infrastructure Partners, a Danish fund manager, has owned a majority of Mulilo since twenty twenty-three.Mulilo will not qualify in its own right, but CIP may respond with Mulilo as part of its consortium.
## Local developers' limited options
Local developers can join a consortium as a member, contribute to financial tests, or work under a qualifying lead with a small stake.
## Manufacturing Circle's concern
Manufacturing Circle Executive Director Philippa Rodseth said: SA Inc should have a primary seat at the table at this critical juncture to leverage our capabilities at every level, including local developers, local contractors and local…

> SA Inc should have a primary seat at the table at this critical juncture to leverage our capabilities at every level
## The transmission precedent
In July twenty twenty-five, the Department of Electricity and Energy issued an RFQ for the Independent Transmission Projects programme, about one thousand sixty-four kilometres of new lines worth roughly seventeen billion rand.
## Transmission's international winners
On fifteen December twenty twenty-five, Minister Kgosientsho Ramokgopa named seven pre-qualified bidders from seventeen respondents, all led by international companies including China's State Grid International Development Company, Spain's Grupo Cobra and Celeo Redes, and India's…
## Time to fix the rules
Clarification questions close on thirty November twenty twenty-six, and responses on twelve January twenty twenty-seven.
## Key takeaway

Eskom's qualification rules for its six gigawatt Green RFQ exclude South African renewable developers from leading bids, repeating a pattern that sidelined local firms in transmission procurement.

---

Summary: Shortify — https://shortify.news/Daily_Maverick/south-africas-renewable-developers-locked-out-of-eskoms-bigg
Reporting: Daily Maverick — https://dailymaverick.co.za/article/2026-11-23-eskom-green-rfq-local-renewable-energy-developers-locked-out-by-eskom-rules

When you use this summary, link the Shortify URL for the summary and credit the reporting to its newsroom.