Cover art for Google ordered to stop Belgium datacentre build

Google ordered to stop Belgium datacentre build

Belgian authorities halt construction on a major Google datacentre after the tech firm continued work without proper planning approval.

Nov 27, 2026

6 cards · 1m 30s · tap to begin

From · · 1m 30s

Google ordered to stop Belgium datacentre build

Belgian authorities halt construction on a major Google datacentre after the tech firm continued work without proper planning approval.

In brief

Belgian authorities halt construction on a major Google datacentre after the tech firm continued work without proper planning approval. Belgian authorities ordered Google to halt datacentre construction in Wallonia after the company continued building without approved permits, with a court ruling expected January…

Google halts Belgium datacentre work

Google halts Belgium datacentre work

Belgian authorities ordered Google to stop construction on a large datacentre in Wallonia after the company continued building without approved planning permission modifications.

Building nearly complete despite permit refusal

Building nearly complete despite permit refusal

Inspectors found the three hectare structure almost finished with structural work completed, even though the permit had been refused. Three hundred workers received verbal and written stop orders.

“Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused”

Google switched cooling method in twenty twenty-five

Google's twenty twenty-five application proposed merging two smaller air-cooled datacentres into one larger facility using water cooling, drawing six hundred cubic metres hourly from the Sambre River.

Permit revoked over drought concerns

Regional authorities initially approved the amendments in April, but residents and protest groups appealed. In August, Wallonia infrastructure minister François Desquesnes revoked the modified permit over drought concerns.

Greenpeace exposed ongoing construction

Greenpeace exposed ongoing construction

Greenpeace published a report with drone footage showing Google continued construction despite lacking correct permits. The environmental group filed an emergency appeal with local planning authorities.

“The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked”

Court ruling expected January seventh

Google appealed the permit revocation to Belgium's council of state. A ruling in the case is expected on seven January, with prosecutors investigating allegations of illegal construction covering three hectares.

The key point

Belgian authorities ordered Google to halt datacentre construction in Wallonia after the company continued building without approved permits, with a court ruling expected January seventh.

Read the original on the Guardian

Read the TL;DR — this story on one card.

How we make summaries

React

Sign in to react and comment.

Comments (0)

Life is short. Keep it sweet. Respect others' opinions and be kind!

    Recommended next

    More decks on google and related topics.