Railways breaks through 6.59-km tunnel in Himalayan rail project

Rail Vikas Nigam Limited completes excavation of Tunnel-14 on the Rishikesh-Karnaprayag line, overcoming challenging geology beneath inhabited areas.

6 cards · 2m · tap to begin

From · · · 2m

Railways breaks through 6.59-km tunnel in Himalayan rail project

Rail Vikas Nigam Limited completes excavation of Tunnel-14 on the Rishikesh-Karnaprayag line, overcoming challenging geology beneath inhabited areas.

In brief

Rail Vikas Nigam Limited completes excavation of Tunnel-14 on the Rishikesh-Karnaprayag line, overcoming challenging geology beneath inhabited areas. Rail Vikas Nigam Limited achieved breakthrough on Tunnel-14, a six point five nine kilometre tunnel in Uttarakhand's Rishikesh-Karnaprayag rail project, using…

Tunnel breakthrough in Uttarakhand

Rishikesh-Karnaprayag railway project: RVNL completes 6.59-km tunnel-14 excavation in Rudraprayag (Image: RVNL)

Rail Vikas Nigam Limited, a Public Sector Undertaking under the Ministry of Railways, achieved breakthrough of Tunnel-14 on Friday in Rudraprayag district, Uttarakhand.

The tunnel measures 6.59 kilometres

Tunnel-14 measures around six point five nine kilometres and is part of the one hundred twenty five kilometre long Rishikesh-Karnaprayag rail project being developed at a total cost of Rs thirty seven thousand one hundred…

Excavating beneath inhabited areas

One major challenge was excavating a one hundred ten metre stretch of the triple-track tunnel through loose soil at Portal-1, where the overburden was only twenty to thirty metres beneath inhabited areas.

Specialised techniques used

Specialised techniques used

Engineers adopted specialised techniques including pre-excavation and multi-drifting to carry out work under challenging ground conditions, and deployed specialised ventilation systems for fresh air supply throughout the four point seven kilometre Portal-1 drive.

Project nearing completion

RVNL Chairman and Managing Director Saleem Ahmad said the Rishikesh-Karnaprayag rail project has achieved seventy-nine percent overall progress, with around ninety-seven percent of tunnel excavation work completed.

Expected benefits after completion

Once completed, the project is expected to improve connectivity to the Himalayan region, facilitate access to Char Dham pilgrimage destinations, strengthen border connectivity, boost tourism and local economies, and significantly reduce travel time across the…

The essence

Rail Vikas Nigam Limited achieved breakthrough on Tunnel-14, a six point five nine kilometre tunnel in Uttarakhand's Rishikesh-Karnaprayag rail project, using specialised techniques to excavate through loose soil beneath inhabited areas.

Read the original on The Indian Express

Read the TL;DR — this story on one card.

How we make summaries

React

Sign in to react and comment.

Comments (0)

Life is short. Keep it sweet. Respect others' opinions and be kind!

    Recommended next

    More decks on rail vikas nigam limited and related topics.